Plan for Play Concept Plans
Last updated 12 November 2026.
Refurbishment & replacement projects 2026
Here we are sharing approved play space concept plans and anticipated timelines for Phase 1 major projects, as they become available. The images below show finalised designs for play spaces at:
Projects currently underway
Starting this month
Once completed, a project’s concept plans are shown below current/scheduled projects – completed projects.
Noyce Gardens
Bournemouth BH8 OJZ
Noyce Gardens is an Urban Replacement Play Space project.
Works started on site 09 September.
Anticipated completion mid November.
Budget £181,500.
Green Road
Old Town Poole BH15 1QN
Green Road is an Urban Refurbishment Play Space project.
Works started on site 05 October 2026.
Completed & re-opening 13 November.
Budget £73,250.
Hamworthy Park
Lulworth Avenue, Poole BH15 4DH
Hamworthy Park is a Neighbourhood / Destination Replacement Play Space project.
Works started on site 12 October.
Anticipated completion 23 December.
Budget £187,900.
Anchor Close
Bournemouth BH11 9HZ
Anchor Close play area is an Urban Refurbishment Play Space project.
Works started on site 26 October.
Anticipated completion mid-November.
Budget £60,000.
Dawkins Road
Carisbrooke Crescent, Poole BH15 4LB
Dawkins Road is an Urban Refurbishment Play Space project.
Works started on site 02 November.
Anticipated completion mid-December.
Budget £95,750.
Alexandra Park
Alexandra Road, Poole BH14 9EW
Alexandra Park is a Neighbourhood Play Space Refurbishment project.
Works started on site 09 November.
Anticipated completion 30 November.
Budget £101,200.
Branksome Rec
Recreation Road, Poole BH12 2EB
Branksome Recreation Ground is an Urban Refurbishment Play Space project.
Works scheduled to start on site 16 November.
Anticipated completion 21 December.
Budget £78,500.
Haskells Recreation Ground
Ringwood Road, Poole BH12 3LH
Haskells Rec play area is an Urban Refurbishment Play Space project.
Anticipated start on site 16 November.
Anticipated completion late December.
Budget £170,300.
Baiter Skatepark
Newfoundland Drive, Poole BH15 1XR
A destination skate and wheeled play facility.
Planning permission granted 29 September – Planning Application No. P/26/02919/FUL | BCP Register
Anticipated start on site 16 November.
Anticipated completion end March 2027.
Budget £400,000.
These are the updated & final (Sept 2026) 3D concept plans
Baiter Skatepark Redevelopment - FAQs
Why isn’t a skate bowl included?
Baiter Skatepark is located on a historic landfill site and in an area of risk of flooding. This limits how much excavation can take place. The design team has focused on creating the best possible riding experience, within the site’s constraints.
Why is there no pump track?
The funding for this project is specifically for improving the existing skatepark. While a pump track is not included in the current scheme, BCP Council has heard the feedback from residents and users and will look to develop this further as part of the next phase of Plan for Play improvements.
Why aren’t my comments included in the revised scheme?
All feedback has been carefully considered. However, not every suggestion can be included. The design must balance different views, the available budget, site constraints and safety requirements. Even if a suggestion has not been included, all comments help inform the project and future improvements.
Why isn’t the entire facility constructed from concrete?
By using a combination of surfaces, we can make the most of the available space and deliver a larger skate park with a wider range of features within the available budget. This approach provides more opportunities for different styles of riding, and offers space for users of different ages and abilities.
The scheme feels too busy – can you remove some of the features? – updated response 10 September
Thank you to everyone who took part in the 13 August consultation and shared their feedback on the skatepark proposals.
Following this engagement, the designs have been refined and re-submitted as part of the planning application process. Updates include a reduction in the number of features within the tarmac area, refinements to the concrete skate area, and changes to the colour scheme in response to comments from local riders.
Completed play space refurbishments
Muscliff Park
Shillingstone Drive, Bournemouth BH9 3LR
Muscliff Park is an Urban Refurbishment Play Space project.
Works started on site 29 September.
Completed & re-opened 12 November.
Budget £134,700.
Churchill Gardens, Phase 1
Bournemouth BH1 4ES
Churchill Gardens is a Neighbourhood Play Space project.
Delivery of this project is phased. Phase 1 (junior play) is indicated on the plan by a red dashed line.
Works started on site 12 October.
Completed & re-opened 05 November.
Budget £60,000.
Kings Park
Ashley Road, Bournemouth BH1 4NN
Kings Park (Ashley Road) is a Neighbourhood / Destination Replacement Play Space project.
Works started on site 01 September.
Completed & re-opened 30 October.
Budget £186,200.
Hatchards Field
Rossmore Road, Poole BH12 2HQ
Hatchards Field is an Urban Refurbishment Play Space project.
Works started on site 14 September.
Completed & re-opened 21 October.
Budget £103,500.
Mallard Road
Bournemouth BH8 9PJ
Mallard Road is an Urban Refurbishment Play Space project.
Works started on site 10 September.
Completed & re-opened 9 October.
Budget £104,000.
Bourne Valley
Turbary Close, Poole BH12 4HD
Bourne Valley is a Natural Play Space Replacement project.
Works started on site 20 July; the play space was completed & reopened 19 August.
Budget £139,800.
Treasure Island
Cliff Drive, Poole BH13 7JF
Treasure Island (aka Pirate Park) is a Themed Replacement Play Space project.
Completed & reopened 20 June 2026.
Budget £130,951 joint funded through Neighbourhood CIL and Canford Cliffs Land Society.
Project details
Updated Budget Phase 1, £4.6 million
Funding Various sources – Community Infrastructure Levy, developer contributions, third-party funding and ring-fenced reserves
Project Leader Rebecca Whelan-Edmonds, Programme Manager, BCP Council
T. 01202 123432
E. greenspaces@bcpcouncil.gov.uk
Follow us on facebook
Plan for Play latest news
Baiter skatepark all set for major transformation
Construction work, led by Maverick, will get underway on 16 November and is expected to last until March 2027. A section of the adjacent carpark will be utilised as a compound for the works. …
Plan for Play Newsletter – September 2026
There’s been a lot happening over the past few weeks as part of our Plan for Play programme – so let’s bring you up to speed …